Project Overview
The Evergreen Playfield Complex is located in the heart of the city. Evergreen Playfield #1, the furthest north field in the complex is a dirt multipurpose field with wood poles and metal halide lighting designed and constructed in the late 1970’s. The city has ranked this project near the top of its list for years as a target for improvements, not only because of its age but also because it serves as an important entry point to the city. The city was awarded multiple grants in 2018 and 2019 to finally make this local dream a reality. This project will include a conversion from the current dirt surface to an synthetic turf surface with drainage, underlayment, infill material, new LED lights, new field fencing, improved pathways and field amenities such as soccer goals, bleachers and corner flags.
Project Timeline and Costs
Design/Construction Firm Selection: November 2019-February 2020
January 21, 2020 Musco Lighting Award at Council
February 11, 2020 Stakeholder meeting #1
February 11-14, 2020 Survey of Site
February 18, 2020 FieldTurf Award at Council
Design Work: February 2020-December 2020
February 24-June 1, 2020 Geotechnical work
June 15-26, 2020 LED Lights Installed
November 9, 2020, 6pm: Public Input Meeting
November 16, 2020: Council review final construction plans
January 4, 2021: Council approved construction contract
January 19, 2021 Construction Begins
Estimated Completion: May 2021
Total estimated cost: $2.178 million